Zara
Westfield
London
Complete
fit-out of new developers shell within a 14 week programme, in conjunction
with Zara's Project Management Team. Works include lift and escalators
installation, mechanical, eletrical and sprinkler works, structural shopfront
works, all internal walls, ceilings, floors and associated finishes, internal
fixturing and store commisioning.
Completed:
October 2008